I have completed almost all of the tasks that I have included in the project plan and made the third pull request. The pull request is for PTM-84 and after doing this task, patient matching module supports to match patients incrementally.    

To complete this task I had to change the MatchingReportUtils.java class in the patient matching module. Those changes can be found here.

What I have done up to now?
So far I have completed,

  • PTM-82 - Load patients for the incremental matching
  • PTM-83 - Generate and save reports in incremental patient matching process
  • PTM-84 - Perform patient match with two datasources